ADDENDUM To: Procurement of Design, Supply and Installation of Grain Steel Silo for Lot # - 1: Design, Supply and Installation of Grain Steel Silo Plant for Herat Province and Lot # - 2: Design, Supply and Installation of Grain Steel Silo Plant for Kandah

mail-admin

د خپریدو نېټه

تاریخ ختم

ADDENDUM No: to IFB No - MAIL/ARTF/SGRP/CS-2019-0011/12

Procurement of Design, Supply and Installation of Grain Steel Silo for Lot # - 1: Design, Supply and Installation of Grain Steel Silo Plant for Herat Province and Lot # - 2: Design, Supply and Installation of Grain Steel Silo Plant for Kandahar and Herat Provinces.

Strategic Grain Reserve Project (SGRP)

Loan No. /Credit No. /Grant No.:P160606

 Addendum No-2 for this procurement is available in these websites. https://www.mail.gov.afhttps://www.npa.gov.af , https://www.undb.org and https://www.acbar.org,   for receiving soft copy of the addendum please contact to Mr. Ziauddin Zia Sr. Procurement Specialist for SGRP/MAIL or Mohammadullah Sahil procurement director of MAIL through the below email address during office hours - 09:00 AM to 15:00 PM hours: ziauddin.zia@mail.gov.af  and mohammadullah.sahil@mail.gov.af.

Propose of the Addendum:

As per pre-bid meeting of Herat and Kandahar silos package which took place on November 17, 2019, most of the companies requested the below changes. In order, to be able to participate in bid opening.

Original Bid

Modified  Bid

Part 1, 3 Bid Document, Page 65 – Section III – Evaluation and Qualification Criteria.

Paragraph 2.7 Subcontractors:

Note: Sub-contractor must meet the following requirements of sub-contracted parts of the contract:

Following requirements of sub contracted parts of the contract:

  • Similar contract in construction of (Civil Work): 90%
  • Annual turnover: 110%
  • Available balance: 30%
  • At least one similar contract in construction of site plan civil work, utilities and facilities of site plan in the last 5 years

“Subcontractor” means any person named in the Contract as a Subcontractor, or any person appointed as a subcontractor, for a part of the Works; and the legal successors in title to each of these persons.

“Contractor’s Personnel” means the Contractor’s Representative and all personnel whom the Contractor utilizes on Site, who may include the staff, labor and other employees of the Contractor and of each Subcontractor; and any other personnel assisting the Contractor in the execution of the Works.

The Contractor shall not subcontract the whole of the Works.

The Contractor shall be responsible for the acts or defaults of any Subcontractor, his agents or employees.

The Contractor shall not be required to obtain consent to suppliers solely of Materials, or to a subcontract for which the Subcontractor is named in the Contract

The Contractor shall introduce not less than 7 days’ from notice to proceed each Subcontractor to mail. The Payment will be executed only for Main contractor after approval of MAIL/SGR technical team to which includes an amount payable to a nominated Subcontractor is executable through Main contractor. 

The Contractor is responsible for all activities addressed to all the Site staff and labor (including all the Contractor's employees, Subcontractors and any other Contractor’s personnel, and all truck drivers and crew making deliveries to Site for construction activities as well as concerning the risks and dangers

Failure to comply with this requirement will result in rejection of the subcontractor.

In the case of a Bidder who offers to supply and install major items of supply under the contract that the Bidder did not manufacture or otherwise produce, the Bidder shall provide the manufacturer’s authorization, using the form provided in Section IV, showing that the Bidder has been duly authorized by the manufacturer or producer of the related plant and equipment or component to supply and install that item in the Employer’s Country. The Bidder is responsible for ensuring that the manufacturer or producer complies with the requirements of ITB 4 and 5 and meets the minimum criteria listed above for that item.

Part 1, 3 Bid Document, Page 65 – Section III – Evaluation and Qualification Criteria.

Paragraph 2.7 Subcontractors: Is amended to,

As per companies request it has decided to bring the following changes:

Note: Sub-contractor must meet the following requirements of sub-contracted parts of the contract:

Following requirements of sub contracted parts of the contract:

  • Similar contract in construction of (Civil Work): 90%
  • Annual turnover: 110%
  • Available balance: 30%
  • At least one similar contract in construction of site plan civil work, utilities and facilities of site plan at  the last 5 years

In case of Having Sub-contractor:

If any Subcontractor is entitled under any contract or agreement relating to the Works, the bidders are obliged to introduce their subcontractor in the proposal during bid opening.

Evidence of Payments for subcontractor:

Before issuing a Payment Certificate which includes an amount payable to a nominated Subcontractor, the Engineer may request the Contractor to supply reasonable evidence that the nominated Subcontractor has received all amounts due in accordance with previous Payment Certificates.

“Subcontractor” means any person named in the Contract as a Subcontractor, or any person appointed as a subcontractor, for a part of the Works; and the legal successors in title to each of these persons.

“Contractor’s Personnel” means the Contractor’s Representative and all personnel whom the Contractor utilizes on Site, who may include the staff, labor and other employees of the Contractor and of each Subcontractor; and any other personnel assisting the Contractor in the execution of the Works.

The Contractor shall not subcontract the whole of the Works.

The Contractor shall be responsible for the acts or defaults of any Subcontractor, his agents or employees.

The Payment will be executed only for Main contractor after approval of MAIL/SGR technical team to which includes an amount payable to a nominated Subcontractor is executable through Main contractor. 

The Contractor is responsible for all activities addressed to all the Site staff and labor (including all the Contractor's employees, Subcontractors and any other Contractor’s personnel, and all truck drivers and crew making deliveries to Site for construction activities as well as concerning the risks and dangers.

Date: November 30, 2019

Time: 10:00 AM, Kabul Local Time

Date: December 14, 2019

Time: 10:00 AM, Kabul Local Time

Mr. Mohammadullah “Sahil” Procurement Director

Procurement Directorate of MAIL                            

Ministry of Agriculture, Irrigation and Livestock 

Jamal Mina, Kabul University Main Road

Kabul - Afghanistan
Telephone: + 93 (0) 202922450

Email: procurement.goods@mail.gov.af